Southeastern Avenue from 18th Street to 26th Street

Project Update 5/29/2020 

Due to COVID-19, weekly meetings will not be open to the public.  If you have questions or concerns, please reach out to the project team. 

  • Contractor continues to work on watermain repair and storm sewer repair.  
  • In the next two weeks, we will begin cement treated base for the west side lanes with curb and gutter and asphalt paving to follow.  

2020 Project Milestones

Phase 1

  • Tree and surfacing removal
  • Installation of sanitary sewer, storm sewer and watermain
     

Phase 1B

  • Closure of Southeastern Ave
  • Pavement removals
  • Storm sewer installation
  • Grading
  • Paving

Phase 2

  • Surface removals
  • Storm sewer installation
  • Grading
  • Paving

Open to Traffic

Commuter Route Information:

  • Southeastern Ave will be closed to thru traffic. 
  • Detour route will be 18th St and Cleveland Ave. 
  • Access will remain open for residents only from 18th Street.  

Phasing Plan Layout 

Project Overview

Contract Amount: $1,505,505    

Completion Date: Fall 2020

Project Summary

This project with consist of reconstruction/widening of Southeastern Ave.  Work will include the removal of existing street surfacing, installation of watermain, storm and sanitary sewer, roadway lighting and traffic signal improvements and asphalt street surfacing.

Contact Information:

City of Sioux Falls
Dena Knutson
dknutson@siouxfalls.org
(605) 367-8630

Consultant 

JSA Consulting Engineers/Land Surveyors, Inc.
Travis Clark
travis@jsaengineers.biz
(605) 367-1036

Contractor Name

Soukup Construction, Inc.