Southeastern Avenue from 18th Street to 26th Street

Project Update 9/25/2020 

Due to COVID-19, weekly meetings will not be open to the public.  If you have questions or concerns, please reach out to the project team. 

  • Contractors are completing the topsoil and seeding, placing mailboxes and signs.
  • Traffic striping be completed this week and will then open to local traffic.
  • This will be the final report.

2020 Project Milestones

Phase 1

  • Tree and surfacing removal
  • Installation of sanitary sewer, storm sewer and watermain

Phase 1B

  • Closure of Southeastern Ave
  • Pavement removals
  • Storm sewer installation
  • Grading
  • Paving

Phase 2

  • Surface removals
  • Storm sewer installation
  • Grading
  • Paving

Open to Traffic

Commuter Route Information:

  • Will be open to local traffic

Phasing Plan Layout 

Project Overview

Contract Amount: $1,505,505    

Completion Date: Fall 2020

Project Summary

This project with consist of reconstruction/widening of Southeastern Ave.  Work will include the removal of existing street surfacing, installation of watermain, storm and sanitary sewer, roadway lighting and traffic signal improvements and asphalt street surfacing.

Contact Information:

City of Sioux Falls
Dena Knutson
dknutson@siouxfalls.org
(605) 367-8630

Consultant 

JSA Consulting Engineers/Land Surveyors, Inc.
Travis Clark
travis@jsaengineers.biz
(605) 367-1036

Contractor Name

Soukup Construction, Inc.