Sertoma Avenue Water Main – 41st Street to 57th Street

Project Update 10/10/2019

  • The project is substantially complete, and has been reopened to traffic.
  • Site restoration, seeding, and other minor miscellaneous items remain to be completed over the next few weeks.
  • Seeding will take place after October 15th. 
  • This will be the final project update.

Project Milestones Have Changed

  1. Milestone 1: Project Start
  2. Milestone 2: Phase A Utilities
  3. Milestone 3: Phase A Grading & Paving
  4. Milestone 4: Phase B Utilities
  5. Milestone 5: Phase B Grading & Paving
  6. Milestone 6: Phase C Utilities
  7. Milestone 7: Phase C Grading & Paving
  8. Milestone 8: Phase A & B Mill & Overlay
  9. Milestone 9: Phase B & C Mill & Overlay
  10. Milestone 10: Phase A and B Striping
  11. Milestone 11: Phase B and C Striping
  12. Milestone 12: Restoration & Cleanup

Commuter Route Information

  • Sertoma Avenue is reopened to commuter traffic.
  • Periodic work may occur over the next couple of weeks to complete miscellaneous construction along the street.
  • However, at least one lane of traffic in each direction will be maintained at all times.
     

Sign Up for Notifications

Project Overview

Contract Amount: $1,288,000    

Completion Date: 9/11/2019

Project Summary

Work will include improvements to the water supply system. Work will also include improvements to various asphalt roadways, curb and gutter, and sidewalk ADA ramps. Upon completion of work, site restoration will take place.

Contact Information:

City of Sioux Falls
Justin Petersen
Jpetersen2@siouxfalls.org
(605) 367-1894

Consultant 

Stockwell Engineers, Inc.
Mitchell Mergen 
mmergen@stockwellengineers.com
(605) 338-6668 (office)

Contractor Name

Winter Brothers Underground