Sertoma Avenue Water Main – 41st Street to 57th Street

Sertoma Avenue Water Main

Project Update 7/18/2019

Milestone dates have changed.

Project Milestones

  1. Project Start Phase A  – 6/17/19
  2. Phase A: Grading & Utilities – 6/20/19 – 7/12/19
  3. Phase B: Grading & Utilities – 7/15/19 – 7/19/19
  4. Phase A: Asphalt Paving – 7/17/19 – 7/18/19
  5. Phase C: Grading & Utilities – 7/24/19 – 8/02/19
  6. Phase B: Asphalt Paving – 7/25/19 – 7/30/19
  7. Phase C: Asphalt Paving – 8/15/19 – 9/7/19

Commuter Route Information

  • All traffic will be detoured to Marion Road effective July 8, 2019.
  • Access to homes will be maintained as construction allows.
  • Traffic Control to be moved north as Phases are completed
     

Sign Up for Notifications

Project Overview

Contract Amount: $1,288,000    

Completion Date: 08/30/2019

Project Summary

Work will include improvements to the water supply system. Work will also include improvements to various asphalt roadways, curb and gutter, and sidewalk ADA ramps. Upon completion of work, site restoration will take place.Contact Information

City of Sioux Falls
Nagwan Al Janabi, Project Manager
NAlJanabi@siouxfalls.org
(605) 367-8643 (office)
(605)-413-7826 (cell) 

Consultant 

Stockwell Engineers, Inc.
Mitchell Mergen 
mmergen@stockwellwengineers.com
(605) 338-6668 (office)

Contractor Name

Winter Brothers Underground