Bluestem Street and 53rd Street (Holbrook Avenue to Marion Road) and Marion Road (53rd Street to 57th Street)
Project Update 2/5/2021
Project Milestones
Phase 1 – Marion Road between 53rd Street and 57th Street
- Install Traffic Control
- Pavement Removals
- Temporary Water Main Installation
- Sanitary Sewer Installation
- Water Main Installation
- Concrete Curb & Gutter/ADA/Sidewalk Installation
- Utility Trench Asphalt Placement
- Mill Remaining Asphalt
- Overlay Entire Street with Asphalt
- Pavement Striping
Phase 2 - 53rd Street between Bluestem Street and Marion Road
- Install Traffic Control
- Pavement Removals
- Temporary Water Main Installation
- Sanitary Sewer Installation
- Water Main Installation
- Concrete Curb & Gutter/ADA/Sidewalk Installation
- Utility Trench Asphalt Placement
Phase 3 - Bluestem Street between Drexel Drive and 53rd Street
- Install Traffic Control
- Pavement Removals
- Temporary Water Main Installation
- Sanitary Sewer Installation
- Water Main Installation
- Concrete Curb & Gutter/ADA/Sidewalk Installation
- Utility Trench Asphalt Placement
Phase 4 - Bluestem Street between Holbrook Avenue and Drexel Drive
- Install Traffic Control
- Pavement Removals
- Temporary Water Main Installation
- Sanitary Sewer Installation
- Water Main Installation
- Concrete Curb & Gutter/ADA/Sidewalk Installation
- Utility Trench Asphalt Placement
Phase 5 – Bluestem and 53rd Street between Holbrook Avenue and Marion Road
- Install Traffic Control
- Mill Remaining Asphalt
- Overlay Entire Street with Asphalt
Commuter Route Information:
Phase 1
- Marion Road will be closed to commuter traffic between 53rd Street and 57th Street during phase 1.
- Access will be maintained for properties within the phase 1 work limits.
- Work on Marion Road is expected to begin this spring, and be complete by mid-June.
Phase 2
- 53rd Street will be closed to commuter traffic between Marion Road and Bluestem Street during phase 2.
- Access for residents will be maintained when possible.
Phase 3
- Bluestem Street will be closed to commuter traffic between 53rd Street and Drexel Drive during phase 3.
- Access for residents will be maintained when possible.
Phase 4
- Bluestem Street will be closed to commuter traffic between Drexel Drive and Holbrook Avenue during phase 4.
- Access for residents will be maintained when possible.
Phase 5
- Bluestem Street and 53rd Street will be closed to commuter traffic between Holbrook Avenue and Marion Road during phase 5.
- Access for residents will be maintained when possible.
Project Overview
Completion Date:
October 22, 2021
Contract Amount:
(Estimated) $1,655,000
Project Summary:
This project consists of replacing the existing water main along Bluestem Street and 53rd Street from Holbrook Avenue to Marion Road, as well as the water main and sanitary sewer along Marion Road from 53rd Street to 57th Street. Street work will consist of miscellaneous curb and gutter repairs, asphalt paving within the water main trench, asphalt patching at various curb and gutter repair areas, milling of the remainder of the street surfacing, and overlaying the entire street segment with asphalt. Accessible curb ramp improvements will also be completed at all intersections within the project limits.
Contact Information
City of Sioux Falls
Tim Krueger
tkrueger@siouxfalls.org
605-940-5280
Consultant Name:
JSA Consulting Engineers and Land Surveyors, Inc.
Devin Clay
devin@jsaengineers.biz
605-690-0035
Contractor Name:
Project will bid spring 2021