Bailey Street – West Avenue to Main Avenue

Phasing Plan

Project Update 10/8/2020

  • Asphalt paving is complete throughout the project and dormant seeding is complete. 

  • The contractor is currently working on some minor cleanup items.

  • This will be the last webpage update for this project.

Project Summary

This project will reconstruct Bailey Street between West Avenue and Main Avenue in order to replace the deteriorated underground utilities and street surfacing. Improvements will include new water main, sanitary sewer, storm drainage piping, accessible curb ramps, curb and gutter repairs, and asphalt surfacing.

Project Milestones

Phase 1A:

  1. Remove existing areas of asphalt and curb/gutter as necessary.
  2. Install new underground utilities.
  3. Replace removed curb/gutter.
  4. Replace asphalt surfacing in disturbed roadway areas.
  5. Topsoil and seed

Phase 1B:

  1. Remove existing asphalt.
  2. Set up temporary water services.
  3. Install new underground utilities.
  4. Grading & gravelling for new roadway.
  5. Replace areas of curb/gutter and driveway approach pavement that were disturbed during utility installation.
  6. Asphalt paving.
  7. Replace areas of sidewalk and pedestrian ramps that were disturbed during utility installation.
  8. Topsoil and seed.

Phase 1C:

  1. Remove existing asphalt and areas of curb/gutter as necessary.
  2. Grading & gravelling for new roadway.
  3. Replace removed curb/gutter.
  4. Asphalt paving.

Phase 2A:

  1. Remove existing asphalt.
  2. Set up temporary water services.
  3. Install new underground utilities.
  4. Grading & gravelling for new roadway.
  5. Replace areas of curb/gutter and driveway approach pavement that were disturbed during utility installation.
  6. Asphalt paving.
  7. Replace areas of sidewalk and pedestrian ramps that were disturbed during utility installation.
  8. Topsoil and seed.

Phase 2B:

  1. Remove existing asphalt.
  2. Set up temporary water services.
  3. Install new underground utilities.
  4. Grading & gravelling for new roadway.
  5. Replace areas of curb/gutter and driveway approach pavement that were disturbed during utility installation.
  6. Asphalt paving.
  7. Replace areas of sidewalk and pedestrian ramps that were disturbed during utility installation.
  8. Topsoil and seed.

Phase 3:

  1. Remove existing asphalt and concrete pavement.
  2. Set up temporary water and sewer services.
  3. Install new underground utilities.
  4. Grading & gravelling for new roadway.
  5. Replace areas of curb/gutter and driveway approach pavement that were disturbed during utility installation.
  6. Concrete paving at intersection of Bailey and Prairie.
  7. Asphalt paving.
  8. Replace areas of sidewalk and pedestrian ramps that were disturbed during utility installation.
  9. Topsoil and seed.

Commuter Route Information:

  • Bailey Street is now open. 
  • Temporary stop signs are placed at the intersection of Bailey Street and Prairie Avenue for Bailey Street drivers until the permanent ones are installed.
     

Project Overview

Completion Date:

Main Avenue to Covell Avenue - November 2020
Covell Avenue to West Avenue – June 2021

Contract Amount: 

Engineers Estimate - $2,550,000

Contact Information

City of Sioux Falls
Raed Yousef
ryousef@siouxfalls.org
605-367-8658

Consultant Name:

Banner Associates
Joe Munson
joem@bannerassociates.com
(605) 941-4276

Alex Welbig
alexw@bannerassociates.com
(605) 261-8212

Contractor Name:

Soukup Construction