69th Street – Louise Avenue to Medical Court

Overview of 69th Street Construction Project

Project Update 12/6/2019

  • All lanes of traffic are now open on 69th Street! 
  • There will be intermittent lane closures over the next few weeks for the installation of light poles and street signs.
  • As weather allows, the contractor will be working on grading in the detention pond north of 69th Street and east of Behavior Health.  
  • Traffic signals will be installed at Mogen Avenue & Beal Avenue when material is available, currently estimating March 2020.
  • This will be the last update for this project webpage until Spring 2020 when the remaining work can be started up again.
     

Project Milestones

  1. Removals, grading, and utility work on the south side of 69th Street between Medical Court and Connie Avenue.
  2. Box culvert installation on the north side of 69th Street, east of Avera Behavioral Health.
  3. Box culvert installation on the south side of 69th Street, west of Beal Avenue.
  4. Final grading, gravel, and concrete paving on the south side of 69th Street between Medical Court and Connie Avenue. 
  5. Asphalt mill and overlay on the south side of 69th Street between Connie Avenue and Louise Avenue.
  6. Final grading, gravel, and concrete paving on Beal Avenue north of 69th Street.  
  7. Removals, grading, and utility work on the north side of 69th Street between Medical Court and Connie Avenue.  
  8. Final grading, gravel, and concrete paving on the north side of 69th Street between Medical Court and Connie Avenue.
  9. Asphalt mill and overlay on north side of 69th Street between Connie Avenue and Louise Avenue. 
  10. Removals, grading, utility work, and asphalt paving on Beal Avenue south of 69th Street.
  11. Final grading and construction of storm drainage structures in the detention pond north of 69th Street and east of Avera Behavioral Health.
  12. Traffic signal installation at 69th Street and Beal Avenue and 69th Street and Mogen Avenue. 
     

Commuter Route Information

(street/intersection closures, detours, etc.)

  • All lanes and accesses are open

Sign Up for Notifications

Project Information

Estimated project cost

$6,155,373.59

Estimated Completion Date

December 2019 (Traffic Signals, February 2020)

Contact Information

City of Sioux Falls
Kari Johnson, Project Manager
kjohnson@siouxfalls.org
(605) 367-8611 (office)
(605) 777-2859 (cell)

Consultant

Stockwell Engineers 
Jon Brown, Project Manager
jbrown@stockwellengineers.com
(605) 338-6668 (office)
(605) 310-2531 (cell)

Ross Kuchta, (on site contact)
rkuchta@stockwellengineers.com
605-338-6668 (office) 
605-310-2533 (cell)

Contractor

T & R Contracting, Inc.