41st Street, Western Avenue to Minnesota Avenue Overlay

Project Update 10/23/2020

  • The project is complete, and all lanes are open to traffic.
  • This will be the last webpage update for this project.

Project Milestones

Phase 1:

  1. Asphalt milling of the outside lanes on 41st Street between Hawthorne Avenue and Minnesota Avenue
  2. Miscellaneous pavement repairs
  3. Asphalt overlay between Hawthorne Avenue and Minnesota Avenue

Phase 2:

  1. Asphalt milling of the inside lanes on 41st Street between Hawthorne Avenue and Minnesota Avenue
  2. Miscellaneous pavement repairs
  3. Asphalt overlay between Hawthorne Avenue and Minnesota Avenue
  4. Pavement markings

Commuter Route Information:

  • All lanes are open to traffic.

Project Overview

Completion Date:

October 16, 2020

Contract Amount: 

$814,959.40

Project Summary:

This project consists of an asphalt mill and overlay on 41st Street from Hawthorne Avenue to Minnesota Avenue.  Work will include milling of the existing asphalt surface, cleaning and patching of existing joints and potholes, placing and asphalt overlay, placing pavement markings on the finished pavement surface, and adjustment of valve boxes, manholes, and junction boxes if necessary.

Contact Infomation