41st Street, Western Avenue to Minnesota Avenue Overlay

Project Update 9/4/2020

  • Asphalt milling of the outside lanes on 41st Street is complete
  • Miscellaneous pavement repairs are underway
  • Asphalt paving will begin for Phase 1 shortly after Labor Day

Project Milestones

Phase 1:

  1. Asphalt milling of the outside lanes on 41st Street between Hawthorne Avenue and Minnesota Avenue
  2. Miscellaneous pavement repairs
  3. Asphalt overlay between Hawthorne Avenue and Minnesota Avenue

Phase 2:

  1. Asphalt milling of the inside lanes on 41st Street between Hawthorne Avenue and Minnesota Avenue
  2. Miscellaneous pavement repairs
  3. Asphalt overlay between Hawthorne Avenue and Minnesota Avenue
  4. Pavement markings

Commuter Route Information:

  • 41st Street is reduced to one lane of traffic in each direction between Minnesota Avenue and Western Avenue
  • Business accesses will remain open as much as possible as work progresses.

Project Overview

Completion Date:

October 16, 2020

Contract Amount: 

$814,959.40

Project Summary:

This project consists of an asphalt mill and overlay on 41st Street from Hawthorne Avenue to Minnesota Avenue.  Work will include milling of the existing asphalt surface, cleaning and patching of existing joints and potholes, placing and asphalt overlay, placing pavement markings on the finished pavement surface, and adjustment of valve boxes, manholes, and junction boxes if necessary.

Contact Infomation

City of Sioux Falls
Josh VandenBos
jvandenbos@siouxfalls.org
605-367-8619

Consultant Name:

Marshall Engineering, Inc.
605-940-0343

Contractor Name:

Asphalt Surfacing Company