Marion Road, Foundation Court to 259th Street

Marion Diagram

Project Update 11/3/2022   

  • The 2022 portion of the project is substantially complete and will open to traffic by the end of this week.
  • The remaining work – power pole relocation, northbound right turn lane, sidewalk and miscellaneous concrete work – will occur 2023.
  • This will be last project update for this year.       

Commuter Route Information: 

  • Marion Road will be opening by the end of this week.

Project Milestones 

Marion Road (2022):

  1. Removals
  2. Water Main
  3. Storm Drainage
  4. Grading
  5. Subgrade Stabilization
  6. Gravel Placement
  7. Concrete Paving
  8. Other Miscellaneous Concrete Work
  9. Future Lighting/Signal Conduit
  10. Pavement Markings
  11. Topsoil & Seeding

259th Street (2022):

  1. Removals
  2. Sanitary Sewer
  3. Water Main
  4. Storm Drainage
  5. Grading
  6. Subgrade Stabilization
  7. Gravel Placement
  8. Asphalt Paving
  9. Miscellaneous Concrete Work
  10. Future Lighting/Signal Conduit
  11. Pavement Markings
  12. Topsoil & Seeding

Northbound Right Turn Lane from Marion Road to 259th Street (2023):

  1. XCEL Energy Power Pole Relocation
  2. Grading
  3. Concrete Paving
  4. Asphalt Paving
  5. Miscellaneous Concrete Work
  6. Pavement Markings
  7. Topsoil & Seeding

 