Marion Road, Foundation Court to 259th Street

Project Update 8/5/2022   

  • The contractor is finishing the borings under the railroad tracks on 259th Street this week. 
  • The contractor is also working on finishing up the storm drainage work on Marion Road, and the waterman and sanitary sewer on 259th Street.

Commuter Route Information: 

  • Marion Road is closed between the north leg of Foundation Court and 259th Street.

Project Milestones 

Marion Road (2022):

  1. Removals
  2. Water Main
  3. Storm Drainage
  4. Grading
  5. Subgrade Stabilization
  6. Gravel Placement
  7. Concrete Paving
  8. Other Miscellaneous Concrete Work
  9. Future Lighting/Signal Conduit
  10. Pavement Markings
  11. Topsoil & Seeding

259th Street (2022):

  1. Removals
  2. Sanitary Sewer
  3. Water Main
  4. Storm Drainage
  5. Grading
  6. Subgrade Stabilization
  7. Gravel Placement
  8. Asphalt Paving
  9. Miscellaneous Concrete Work
  10. Future Lighting/Signal Conduit
  11. Pavement Markings
  12. Topsoil & Seeding

Northbound Right Turn Lane from Marion Road to 259th Street (2023):

  1. XCEL Energy Power Pole Relocation
  2. Grading
  3. Concrete Paving
  4. Asphalt Paving
  5. Miscellaneous Concrete Work
  6. Pavement Markings
  7. Topsoil & Seeding

Project Overview

Completion Date:

November 18, 2022 for the through traffic lanes. 
The turn lanes at North Marion Road & 259th Street will be completed by November 17, 2023 (after XCEL relocates their electrical poles)

Contract Amount: 

$3,252,767.76

Project Summary:

This project will reconstruct Marion Road from a gravel rural section road to an urban concrete pavement section with turning lanes from Foundation Court to 259th Street.  259th Street will also be reconstructed as an asphalt-surfaced street from Marion Road to just east of the railroad tracks.  Work on the project will also include a storm drainage system, sanitary sewer, and water main.  These improvements are necessary to accommodate anticipated traffic increases due to recent and future development at Foundation Park.

Contact Information

City of Sioux Falls
Shane Balk
sbalk@siouxfalls.org
Office:  605 367-8608 
Cell: 605 941-1132

Consultant Name:

Sayre Associates, Inc.
Scott Schnieder
scotts@sayreassociates.com
Office:  605 332-7211 
Cell:  605 940-1051  

Contractor Name:

D & G Concrete Construction, Inc.