Arrowhead Parkway and Six Mile Road Reconstruction

Project Update 8/5/2022  

  • The Contractor is continuing with utility installation along the future Arrowhead Parkway alignment. 
  • Arrowhead Parkway will remain closed from Six Mile Road to Willow Run for another couple of months to allow the contractor to install a large diameter storm drainage crossing.
  • Grading and utility installation continues along the remainder of Arrowhead Parkway.
  • The contractor is currently working on paving Six Mile Road so it can be reopened to traffic by mid-August.
  • 10th Street is closed from Arrowhead Parkway to Tumble Creek Circle to allow utilities to be installed. 
  • 10th Street will reopen to traffic by in early August.  
  • Access to local businesses will remain open. 
  • Please follow detour routes

Commuter Route Information:  

  • Arrowhead Parkway is closed between Six Mile Road and Willow Run.
  • The detour route is along Veterans Parkway and 26th Street.
    Arrowhead Parkway will reopen to traffic in October. 

  • Access along Arrowhead Parkway will be maintained to local traffic and businesses from the west.  
  • Six Mile Road is closed north and south of Arrowhead Parkway and will reopen in mid-August.
  • Traffic will be detoured to Veterans Parkway.
  • Access will be maintained to local traffic throughout the project.
  • 10th Street is closed to from Arrowhead Parkway to Tumble Creek Circle. 
  • A detour will not be provided. 
  • 10th Street will reopen to traffic by in early August.  

Project Milestones 

North side of Arrowhead Parkway

  1. Removals
  2. Water Main
  3. Storm Drainage
  4. Grading
  5. Gravel
  6. Concrete Paving
  7. Other Miscellaneous Concrete Work
  8. Restoration

Six Mile Road

  1. Removals
  2. Sanitary Sewer
  3. Water Main
  4. Storm Drainage
  5. Grading
  6. Gravel
  7. Concrete Paving
  8. Median
  9. Other Miscellaneous Concrete Work
  10. Restoration

South side of Arrowhead Parkway

  1. Removals
  2. Water Main
  3. Storm Drainage
  4. Grading
  5. Gravel
  6. Concrete Paving
  7. Median
  8. Other Miscellaneous Concrete Work
  9. Restoration

Frontage Road

  1. Removals
  2. Sanitary Sewer
  3. Grading
  4. Gravel
  5. Asphalt Paving
  6. Restoration

Project Overview

Completion Date:

September 29, 2023

Contract Amount: 

$21,795,294.94

Project Summary:

This project will reconstruct and widen Arrowhead Parkway from E. 10th Street to the Willow Run Golf Course entrance, and also reconstruct, widen, and realign Six Mile Road to cross Arrowhead Parkway at a safer angle. Improvements include new water main, sanitary sewer, storm drainage, street lights, traffic signals, curb and gutter, and concrete surfacing.

Contact Information

City of Sioux Falls
Tim Krueger 
tkrueger@siouxfalls.org
605-367-8615 (office)
605-940-5280 (cell)

Consultant Name:

Infrastructure Design Group 
Krista May
kristam@infrastructuredg.com
605-271-5527 (office)
605-929-0267 (cell)

Contractor Name:

T&R Contracting, Inc