2022 ADA Accessibility Improvements

Project Update 8/5/2022 

  • Work on the east side of Minnesota Avenue between 37th Street and 41st Street is complete. 
  • Work is in progress on the east side of Minnesota Avenue between 33rd Street and 37th Street.

Commuter Route Information: 

  • The outside northbound lane of Minnesota Avenue is closed between 33rd Street & 37th Street.  
  • Southbound traffic will not be impacted at this time.

Project Milestones  

  1. Sidewalk ADA accessibility repairs along the east side of Minnesota Avenue between 41st Street and 37th Street.
  2. Sidewalk ADA accessibility repairs along the east side of Minnesota Avenue between 37th Street and 33rd Street.
  3. Sidewalk ADA accessibility repairs along the west side of Minnesota Avenue between 37th Street and 33rd Street.
  4. Sidewalk ADA accessibility repairs along the west side of Minnesota Avenue between 41st Street and 37th Street.

Project Overview

Completion Date:

October 28, 2022

Contract Amount: 

TBD

Project Summary:

This project consists of ADA Accessibility Improvements along Minnesota Avenue between 41st Street and 33rd Street.  Work will include ADA accessible curb ramps, landings, and fillet sections, ADA accessible sidewalks with corresponding approach and driveway restorations, concrete curb and gutter repairs and street lighting improvements.

Contact Information

City of Sioux Falls
Tallon Cazer
tcazer@siouxfalls.org
(605)367-8609

Consultant Name:

JSA Engineers and Land Surveyors
Travis Clark
Travis@jsaengineers.biz
Office: (605) 367-1036

Contractor Name:

Precision Concrete, LLC