Lake Ave 5th Street to 6th Street

Project Update 5/15/2020

Project Milestones

  1. Remove existing areas of asphalt and curb/gutter as necessary
  2. Install new underground utilities.
  3. Replace removed curb/gutter.
  4. Replace asphalt surfacing in disturbed roadway areas.
  5. Topsoil and seed

Commuter Route Information

During construction the project will require a full street closure with no vehicle access for residents. Residents will be required to park on a side street during construction. A temporary driveway will be placed for the parking lot of 401 N Lake Avenue off of West Avenue. The project will be completed in approximately 6 weeks. The work is anticipated to begin sometime in early July and completed by mid-August 2020. The actual construction schedule and completion date is dependent upon weather conditions throughout the summer. 

Project Overview

Contract Amount: $297,625.75 

Completion Date: September 30, 2020

This project is for the rehabilitation of the sanitary sewer, water main, and storm sewer in Lake Ave from 5th Street to 6th Street. Due to the existing deteriorated condition of the utilities it is important to replace this line before any further maintenance issues arise. Improvements include new sanitary sewer, water main, storm sewer, curb and gutter, and asphalt surfacing.  

Contact Information

City of Sioux Falls
Allyn Brummel
Abrummel@siouxfalls.org
(605) 367-8648

Consultant
Marshall Engineering
Marshall Runge
marshall.marshalleng@midconetwork.com
 (605) 940-0343 

Contractor Name
Backhaus Construction