Highland Addition Improvements – Phase 3
Project Update 6/29/2022
- Project hasn't started yet.
- Project is expected to start around early July
Commuter Route Information:
- The project will be constructed in 3 phases.
- Residents will not have vehicle access to their residences while construction is taking place.
- Sidewalk access will be maintained at all times.
Project Milestones
Phase 1: Sherman Avenue from 3rd Street to 4th Street
- Removals
- Watermain installation
- Sanitary sewer installation
- Grading
- Subgrade stabilization
- Gravelling
- Paving
- Restoration
Phase 2:Sherman Avenue from 5th Street to 6th Street
- Removals
- Watermain installation
- Sanitary sewer installation
- Grading
- Subgrade stabilization
- Gravelling
- Paving
- Restoration
Phase 3: Wayland Avenue form 5th Street to 6th Street
- Removals
- Watermain installation
- Sanitary sewer installation
- Grading
- Subgrade stabilization
- Gravelling
- Paving
- Restoration
Project Overview
Completion Date:
Fall 2022
Contract Amount:
$811,147.59
Project Summary:
The project will reconstruct Sherman Avenue from 3rd Street to 4th Street, Sherman Avenue from 5th Street to 6th Street, and Wayland Avenue from 5th Street to 6th Street. Improvements will include the removal and replacement of the curb & gutter, asphalt pavement, sanitary sewer, and watermain.
Contact Information
City of Sioux Falls
John Osman
josman@siouxfalls.org
605-367-8601
Consultant Name:
Ulteig Engineers, Inc.
Project Engineer:
Chad Stensland
chad.stensland@ulteig.com
Office: 605 323 6022
Cell: 605 359 7779
On Site Representative:
Enock Ariko
Email: enock.ariko@ulteig.com
Office: (605) 323-6054
Cell: 712-578-1975
Contractor Name:
H & W Contracting, LLC