Highland Street and Utility Improvements – Phase 2

Project Update 6/10/2021

  • The project includes a variety of improvements including the removal and replacement of the curb & gutter, pavement, sanitary sewer, watermain, and storm sewer.
  • The accessible curb ramps will also be replaced. 
  • The project will be constructed in three phases in order to maintain access to residents as much as possible.
  • Construction will tentatively begin on Phase 1, Wednesday June 23, 2021.

Commuter Route Information: 

Sherman Avenue, Pearl Street & Wayland Avenue:

  • This work will be separated into three phases to minimize impacts to residents. 
  • In each phase residents will not have vehicle access to their residences while construction is taking place. 
  • Sidewalk access will be maintained at all times.

6th Street & Lowell Avenue:

  • This work will require a full closure of the intersection to traffic. 
  • 6th Street traffic will be detoured to 10th Street by way of Cliff Avenue and Cleveland Avenue.
  • Residents in the vicinity will have vehicle and sidewalk access at all times. 
  • Lowell Avenue will be closed to through traffic.

Project Milestones 

  1. Phase 1:  Sherman Avenue from 4th Street to 5th Street
  2. Phase 2:  Pearl Street from Sherman Avenue to Wayland Avenue & Wayland Avenue from 4th Street to Pearl Street.
  3. Phase 3:  Wayland Avenue from Pearl Street to 5th Street.
  4. Phase 4:  6th & Lowell Intersection
     

Project Overview

Completion Date:

Fall 2021

Contract Amount: 

$1,453,527.47 

Project Summary:

The project includes a variety of improvements including the removal and replacement of the curb & gutter, pavement, sanitary sewer, watermain, and storm sewer. The accessible curb ramps will also be replaced.  The project will be constructed in three phases in order to maintain access to residents as much as possible.

Contact Information

City of Sioux Falls
John Osman
josman@siouxfalls.org 
Office: 605-367-8601

Consultant Name:

Ulteig
Project Engineer:
Chad Stensland
chad.stensland@ulteig.com
Office:  605-323-6022  
Cell:  605-359-7779

On Site Representative:
Morgan Wrasper
Morgan.Wrasper@ulteig.com
Office:  605-332-0669  
Cell:  605-270-1049

Contractor Name:

H&W Contracting, LLC