Cliff Avenue Rehabilitation from East 26th Street to East Pam Road

Cliff Ave

Download Cliff Avenue Project Phasing

Project Update 6/24/2022  

  • Phase 4 (26th Street Intersection) curb & gutter and fillet repairs, PCC panel and joint repairs, partial depth pavement repairs and accessible sidewalk repair work is currently in progress and will be ongoing over the next week. 
  • Phase 1 (Cliff Avenue 26th Street to Pam Road) curb & gutter and fillet repairs, PCC panel and joint repairs, partial depth pavement repairs and accessible sidewalk repair work is currently in progress and will be ongoing over the next few weeks.
  • Phase 5 (33rd Street Intersection) curb & gutter and fillet repairs, PCC panel and joint repairs, partial depth pavement repairs and accessible sidewalk repair work is currently in progress and will be ongoing over the next few weeks. 

Commuter Route Information: 

  • The westbound driving lane of 26th Street between Cliff Avenue and 10th Avenue is closed. Traffic will be maintained in the center turning lane and eastbound driving lanes. The work will be completed in the next week. At a minimum, one lane of traffic in each direction will remain open at all times. Access to businesses will be maintained.
  • The southbound driving lanes of Cliff Avenue from 26th Street to Pam Road are closed. Two-way traffic will be maintained head to head on the northbound driving lanes.
  • The westbound driving lane of 33rd Street at Cliff Avenue is closed. Traffic will be maintained in the center turning lane and eastbound driving lanes. The work will be completed in the next few weeks. At a minimum, one lane of traffic in each direction will remain open at all times. Access to businesses will be maintained.

Project Milestones 

Phase 1: Cliff Avenue outside southbound driving lanes and curb & gutter

  1. Curb & gutter and fillet repairs.
  2. PCC panel and joint repairs.
  3. Partial depth pavement repairs.
  4. Accessible sidewalk repairs.
  5. Topsoil Placement
  6. Pavement Markings

Phase 2:  Cliff Avenue outside northbound driving lanes and curb & gutter

  1. Curb & gutter and fillet repairs.
  2. PCC panel and joint repairs.
  3. Partial depth pavement repairs.
  4. Accessible sidewalk repairs.
  5. Topsoil Placement
  6. Pavement Markings

Phase 3:  Cliff Avenue northbound and southbound inside driving lanes and center turn lane where applicable

  1. Curb & gutter and fillet repairs.
  2. PCC panel and joint repairs.
  3. Partial depth pavement repairs.
  4. Accessible sidewalk repairs.
  5. Topsoil Placement
  6. Pavement Markings

Phase 4:  East 26th Street intersection

  1. Curb & gutter and fillet repairs.
  2. PCC panel and joint repairs.
  3. Partial depth pavement repairs.
  4. Accessible sidewalk repairs.
  5. Topsoil Placement
  6. Pavement Markings

Phase 5:  East 33rd Street intersection

  1. Curb & gutter and fillet repairs.
  2. PCC panel and joint repairs.
  3. Partial depth pavement repairs.
  4. Accessible sidewalk repairs.
  5. Topsoil Placement
  6. Pavement Markings

Project Overview

Completion Date:

August 13, 2022

Contract Amount: 

$2,921,000.00

Project Summary:

This project will rehabilitate Cliff Avenue between East 26th Street and East Pam Road.  Work will include full depth concrete patching, partial depth concrete patching, curb and gutter repair, sidewalk accessible curb ramp replacement, and pavement markings. This project will also update the pedestrian push buttons to accessible pedestrian signal push buttons. These APS buttons use audible tones to communicate when a pedestrian should cross the street.  

Contact Information

City of Sioux Falls
Michell Knoll
mknoll@siouxfalls.org 
605-367-8632

Consultant Name:

Marshall Engineering Inc.
Marshall Runge, PE
marshall.marshalleng@midconetwork.com
605-940-0343

Contractor Name:

Dakota Contracting Corporation