Airport Industrial Park Utility Improvements Project

Project Update 6/17/2022   

  • The contractor will work on paving of Phase 1 and Phase 2 this week and early next week.
  • The phases will be fully opened to traffic after.  
  • Removals on Phase 5 and Phase 9 have been performed.
  • Phase 5 is currently a lane closure and is allowing through traffic.
  • Work in this phase should take a few weeks.
  • Phase 9 is closed to through traffic.
  • Work in this phase should take a few weeks.

Commuter Route Information:  

  • Expect closures at streets shown in the phases in the above map. 
  • The contractor will be allowed to work on two phases at a time, with some restrictions on which phases can be closed concurrently.  
  • There are other projects going on in this area currently as well. 
  • Coordination is happening between projects to allow access to businesses in the area. 

Project Milestones  

  1. Phase 1
  2. Phase 2
  3. Phase 3
  4. Phase 4
  5. Phase 5
  6. Phase 6
  7. Phase 7
  8. Phase 8
  9. Phase 9

Project Overview

Completion Date:

September 30, 2022

Contract Amount: 

$2,777,230.65

Project Summary:

This project consists of various water, sanitary sewer, and storm sewer improvements throughout the airport industrial park. Work will include replacement and abandonment of water main, upgrading of sanitary and storm sewer, pavement patching and restoration of disturbed areas.

Contact Information

City of Sioux Falls
Raed Yousef
RYousef@siouxfalls.org
605-367-8658

Consultant Name:

Stockwell Engineers, Inc.
rkuchta@stockwellengineers.com
605-310-2533

Contractor Name:

Winter Contracting, LLC