51st Street and Holbrook Avenue Watermain Improvements

Update: 7/2/2020  

  • There was a delay with completing the underground utilities, but that work is now complete. 
  • Street grading, concrete curb and asphalt surfacing will now begin on 51st Street.
  • Work along Holbrook Avenue will begin on Monday, July 6.

Commuter Route Information

  • 51st Street is closed between Holbrook Avenue and Drexel Drive, including the intersection of 51st & Drexel.
  • Holbrook Avenue from 50th Street to 52nd Street will be closed beginning July 6.

2020 Project Milestones

Phase 1:

  1. Traffic Control and Erosion Control Installation
  2. Removal of Street Surfacing
  3. Installation of Sanitary Sewer
  4. Installation of Water Main
  5. Aggregate Base Course Placement
  6. Asphalt Surfacing
  7. Topsoil and Seeding

Phase 2:

  1. Traffic Control and Erosion Control Installation
  2. Removal of Street Surfacing
  3. Installation of Sanitary Sewer
  4. Installation of Water Main
  5. Aggregate Base Course Placement
  6. Asphalt Surfacing
  7. Topsoil and Seeding

Project Overview

Contract Amount: $987,157.20

Completion Date: August 7, 2020

This project will take place along 51st Street from Holbrook Avenue to Drexel Drive and along Holbrook Avenue from 50th Street to 52nd Street.  It will include new water main, new sewer main, full street width asphalt replacement, curb repairs, new street lights, and ADA sidewalk improvements

Contact Information

City of Sioux Falls
Tim Krueger
tkrueger@siouxfalls.org
(605) 940-5280

Consultant Name:
Marshall Engineering
Marshall Runge
marshall.marshalleng@midconetwork.com 
(605)-940-0343 (cell) 

Contractor Name:
ASCO