17th Street and Walts Avenue Improvements

Project Update 7/30/2021 

  • Over the last couple of weeks, the contractor has completed one of two bores under the railroad tracks, and has made significant progress on the underground utility installation. 
  • Work on the underground utilities will continue for the next few weeks.
  • Work on 17th Street between Menlo Avenue and Walts Avenue is now scheduled to begin on Monday, August 2.

Commuter Route Information: 

  • Walts Avenue is closed between 12th Street and 14th Street.
  • 17th Street will be closed from Menlo Avenue to Walts Avenue beginning on Monday, August 2.

Project Milestones

Walts Ave

  1. Road Closure – construction begins
  2. Surface removal
  3. Watermain and service installation
  4. Sanitary sewer main and installation
  5. Aggregate base course
  6. Asphalt paving
  7. Road Open – Construction complete

17th Street

  1. Road Closure – construction begins
  2. Asphalt surface removal
  3. New asphalt surface placement
  4. Road Open - Construction complete
     

Project Overview

Completion Date:

17th Street:  August 20, 2021
Walts Avenue:  October 8, 2021

Contract Amount: 

$1,099,594.37

Project Summary:

Walts Avenue will include surface removal, installation of new water main, sanitary sewer, and street lights, placement of new asphalt surfacing, and accessible curb ramp improvements at the railroad crossing. 

17th Street will include asphalt surface removal, new asphalt surfacing, and accessible ramp improvements at Menlo Avenue. 

Contact Information

City of Sioux Falls
Chad Comes
605-367-8630
ccomes@siouxfalls.org

Consultant Name:

Marshall Engineering
Project Engineer:
Marshall Runge
605-940-0343
marshall.marshalleng@midconetwork.com

Contractor Name:

Backhaus Excavation and Underground, LLC
605-929-0012
neil@backhausexcavation.com