Arrowhead Parkway, Sycamore Avenue to Highline Avenue

Arrowhead Phase Map

Median

Update:4/19/2019

Crews will begin working on Arrowhead Parkway starting Monday, April 22nd. Sidewalk installation, median installation and final grading work remains.

Project Milestones

  1. Roadway surfacing from Sycamore Avenue to Veteran’s Parkway
  2. Sidewalk installation on north side of Arrowhead Parkway
  3. Sidewalk installation on south side of Arrowhead Parkway
  4. Pedestrian push buttons and signal installation
  5. Final roadway striping
  6. Landscaping and median element installation along Arrowhead Parkway
     

Commuter Route Information

Outside westbound lane and inside eastbound lane will be closed starting next week.

Sign Up for Notifications

Project Overview

Estimated Completion Date:

July 2019 

Contract Amount:

$9,370,863.63 

Project Summary:

Reconstruct Arrowhead Parkway to a 6-lane urban street with center median, street lights, traffic signals, and concrete sidewalks.  New water main and storm sewer will also be installed.  Additional right and left turn lanes will be constructed at multiple intersections along Arrowhead Parkway to increase traffic capacity and improve safety. 

Contact Information

City of Sioux Falls

Josh VandenBos, Project Manager
jvandenbos@siouxfalls.org,
605-367-8619 (office)

Consultant Name:
Infrastructure Design Group Inc.
Eric Lerssen
ericl@infrastructuredg.com
605-212-5381 (cell)
605-271-5527 (office) 

Contractor Name

T&R Contracting Inc.