Street Construction News

Rescheduled Minnesota Avenue Pavement Repairs Fire Station 3 at 37th Street

Beginning on Friday, April 20, 2018, at 8:30 a.m., work will begin to replace the driveway approach for Fire Station 3 located at Minnesota Avenue and 37th Street. This work was originally scheduled to begin on Monday, April 16, 2018.

Northbound traffic will be reduced to one lane.

Work will include replacement of the removal and replacement of the concrete driveway approach. Sidewalk will also be replaced from the driveway south to 37th Street. Work is anticipated to be complete in 25 working days.

Drivers are urged to use caution and reduce their speed while travelling near the construction area and may want to consider alternate routes.